Analysis
Aus HITGuard User Guide
Weitere Optionen
Experts can see all organizational units of the active management system that have measures assigned to them under "Measures → Analysis", including an evaluation of those measures in an analysis period.
% overdue:
- The percentage of overdue measures of the selected analysis period, out of the total.
% finished:
- The percentage of finished measures of the selected analysis period.
Overdue of open and new %:
- The percentage of overdue measures among the open ones of the selected analysis period. For example, if there are still 10 open measures and 2 are overdue (mentioned deadline is in the past and the measure has not been implemented), then 20% of the open measures would be overdue.
Ø of progress of open measures:
- The average reported progress of open measures of the selected analysis period. For example, if there are 10 open measures, 3 of which are 50% implemented, 4 are 20% implemented, and the last 3 are 100% implemented, then the average progress is: (3 * 0.5 + 4 * 0.2 + 3 * 1) / 10 = 53%.
Ø of growth of the progress of open measures:
- The average reported progress trend of open measures of the selected analysis period as compared to that of the previous analysis period. If a measure was 20% implemented in the previous analysis period and in this one the implementation has increased to 70%, then the growth of progress in this case is 50%.
If you do not see the points listed above, you can scroll to the right within the table with the scrollbar. Also make sure that the desired columns are displayed (the column chooser is next to the search bar).