KO measures always count as HIGH and are those that must be implemented immediately as the vulnerabilities are linked to a very high attack potential.

Of course, not the same effort can be assumed for the implementation of every measure. Projects are therefore classified as follows, depending on their planned duration and the estimated project days:

  1. SMALL: <1 month duration; <= 2 PD effort
  2. MEDIUM: <3 months duration; <= 10 PD effort
  3. LARGE: >3 months duration; > 10 PD effort

Therefore, only a recommended timeframe is given here.

Considering the factors criticality and effort, the following maximum reocmmended implementation timeframe is given:

Effort
Criticality LARGE MEDIUM SMALL
LOW 4 months + project effort 7 months 5 months
MEDIUM 2 months + project effort 5 months 3 months
HIGH project effort 3 months 1 month